2026 Capital Projects
Six water main replacements are in process in the Leawood subdivision. Diaz Construction has completed 75% of the pipe installation. The sections on S. Marshall Dr. and S. Lamar Dr. have been completed. Diaz has proceeded to W. Burgundy Dr. and then following with S. Newland St., then S. Nixon Ct. and lastly S. Otis Ct.